Typical Project Timeline_____________________

  • Engineer & Permit
    AVG TIME: 8 WEEKS

    OnSwitch creates a detailed design of your system that is reviewed and approved by the local permitting agency and utility. Solar carports usually take longer to permit than rooftop solar.

  • Procure
    AVG TIME: 6 WEEKS

    OnSwitch orders the solar panels, inverters, racking and monitoring equipment for your solar system. Lead times for all components are typically less than 6 weeks, although steel for solar carports could take a few weeks longer.

  • Install
    AVG TIME: 8-10 WEEKS

    The major installation work lasts only a few weeks, followed by smaller tasks and testing, and ending with a visit by the utility for final approval of your solar system for operations.